JPS, LLP performed the Structural engineering for the backstage and auxiliary buildings. JPS, LLP performed the Geotechnical engineering for the entire complex. The 5,000 seat arena and stage consist of exterior structural concrete slab construction supported by driven steel H-piles due to very poor site conditions atop Solvay Waste landfill material. The $50M design build project required an accelerated schedule including only 6 months of construction.